Migrate to NexCMP with an expert engineer

Moving a live cloud business is mostly planning, testing and a careful cutover. With the NexCMP Source upgrade you get 30 working days of continuous work with an expert engineer, who migrates you from VMware to Apache CloudStack, from WHMCS to NexCMP, or from any other billing panel, at no extra charge.

Included with NexCMP Source only, not with NexCMP Free. VMware, WHMCS, HostBill, Blesta, Paymenter, StackBill, Virtualizor and Apache CloudStack are trademarks of their respective owners. NexCMP is independent and not affiliated with or endorsed by them.

Why migrations stall

Most teams know where they want to be: virtual machines on Apache CloudStack, customers and billing in one self-hosted system. What stops them is the move itself. Virtual machines have to be converted and tested, customer balances and services have to be carried over exactly, and the day billing switches over has to be chosen so nobody is charged twice or not at all.

A migration is also easy to underestimate, because the work is spread over inventory, a target environment, trial runs, several waves of moves and a final cutover. Doing it with an engineer who has done the steps before keeps it a plan with dates instead of a side project.

What we can migrate for you

Pick the one that matches where you are today. Each page explains what moves, the plan week by week, the risks and what we need from you.

  • VMware to Apache CloudStack

    Plan and run the move of virtual machines from VMware vCenter into a CloudStack zone, using the import and conversion features that CloudStack itself provides. Cutover is planned VM by VM.

  • WHMCS to NexCMP

    Read customers, credit balances, services and plans out of WHMCS and rebuild them in NexCMP, then run both systems side by side until you switch billing over. NexCMP is not WHMCS, so the page says plainly what is rebuilt and what is archived.

  • Any other system or billing panel

    HostBill, Blesta, Paymenter, StackBill, Virtualizor or a system of your own: the same method of inventory, export, mapping, dry run and cutover.

  • Full A-to-Z setup and branded apps

    If you would rather have the whole system set up for you, and every app built under your brand, the same 30 working days can be used for that instead.

What is included, and what is not

The service belongs to one edition only.

  • Price

    NexCMP Free
    $0 for the first year; renews at $99 per year, a token fee for fixes of source-code bugs.
    NexCMP Source
    $499, one-time purchase.

    Source: nexcmp.com/pricing · accessed 2026-10-19

  • Modules

    NexCMP Free
    All modules.
    NexCMP Source
    All modules, plus the complete source code and the right to modify and build your own version without limit.
  • Technical support

    NexCMP Free
    None. Only fixes of source-code bugs.
    NexCMP Source
    30 working days of continuous work with an expert engineer, and support for the move for the same 30 days.
  • Migration and expert setup

    NexCMP Free
    Not included.
    NexCMP Source
    Included at no extra charge: VMware to CloudStack, WHMCS to NexCMP, any other source system to NexCMP, or a full A-to-Z setup.
  • Apps

    NexCMP Free
    Building and branding the apps for you is not part of Free.
    NexCMP Source
    Apps for Android, Windows, macOS, Linux, Chrome/Edge/Brave and Firefox (iOS is Soon), built and branded for you.
  • New source releases

    NexCMP Free
    Not applicable.
    NexCMP Source
    12 months.

The migration and expert service is not part of NexCMP Free. It comes only with NexCMP Source. The 30 working days start when you begin the work with the expert; the date is shown on your license page. Thirty working days is about six calendar weeks.

A typical plan, week by week

Typical, adjusted to your case. The first week produces the real plan, with your systems, your constraints and your dates in it.

  1. Week 1 — Inventory and plan

    We read what you have: virtual machines, customers, services, plans, payment gateways. Together we decide what moves, what is rebuilt, what is archived, and the order of the waves.

  2. Week 2 — Build the target

    The target environment is prepared: the CloudStack zone, or the NexCMP install with your branding, plans and payment channels. Nothing is switched yet.

  3. Week 3 — Pilot and dry run

    A few non-critical virtual machines or a copy of the customer data go through the real procedure. We measure how long each step takes and fix what the trial shows.

  4. Weeks 4 and 5 — Waves

    The rest moves in groups, each at an agreed time and each checked before the next begins. Old systems stay untouched so you can go back.

  5. Week 6 — Cutover and handover

    Billing is switched on the date you chose, DNS and customer notices are sent, and we hand over notes on how everything was done. Support for the move lasts until day 30.

Six weeks is a typical length for 30 working days, not a promise about any one project. The 30-working-day clock is the only commitment in the offer.

Who does what

  • A NexCMP Source license and the date you want to start

    The expert does
    Plans the work and keeps the 30 working days moving continuously
  • Read access to the source system: vCenter, WHMCS admin, or the other panel

    The expert does
    Inventories it, exports the data and maps it to NexCMP
  • Access to the target servers, CloudStack and, where relevant, payment gateway accounts

    The expert does
    Builds and tests the target, runs the dry run and the waves
  • Decisions: which services move, the cutover date, customer communication

    The expert does
    Proposes options with their risks, then carries out your choice
  • Someone who can answer questions about your customers and plans during the project

    The expert does
    Documents what was done so your team can run it afterwards

Risks and how we reduce them

A migration cannot promise zero downtime. These are the risks that matter and how each one is handled.

  • Cutover downtime

    Moving a virtual machine means stopping it for some time. We test the procedure in the pilot to see how long it takes, and then agree a window per group of machines with you. We do not promise zero downtime.

  • Addresses and DNS

    IP addresses and network settings can change when a machine moves. We list them in week 1, lower DNS TTLs before the cutover and tell your customers in advance.

  • Billing cut-over

    The day billing moves is chosen with you. Both systems run side by side beforehand, and subscriptions at the old billing system are ended on the cutover day so nobody pays twice.

  • Guest software and licenses

    Drivers change when a machine changes platform, and licenses of the software inside the machine can be tied to the old platform. We list both in the inventory so you can check them with the software vendors.

  • Rollback

    The original systems are kept until you agree the move is finished, so every group has a way back.

How to start

Upgrade your license to NexCMP Source, then tell us which migration you need. If you have questions first, write to [email protected] or open the contact page and describe your current systems in a few lines.

Migration service — frequently asked questions

What does it cost?
The migration is part of the NexCMP Source upgrade, which costs $499 one-time. That price includes the complete source code, the right to modify and build your own version without limit, 12 months of new source releases, all apps and 30 working days of work with an expert engineer. The offer has no hourly fees.
Is this included in NexCMP Free?
No. The migration and expert service comes only with NexCMP Source. NexCMP Free is free for one year with all modules, has no technical support (only fixes of source-code bugs), and renews at $99 per year.
How long does it take?
The offer is 30 working days of continuous work with the engineer, about six calendar weeks. The clock starts when you start the work with the expert and is shown on your license page. The first week turns the typical plan into one for your case.
Can you migrate with no downtime?
We do not promise that. Moving a virtual machine means stopping it for a while, and switching billing has to happen on one day. We reduce the risk with a pilot, measured timings, agreed windows per group, a billing parallel run and a way back to the old systems.
What do I need to provide?
Access to the source system (read access is enough to start), access to the target servers and accounts, and someone who can decide which services move and when. Each migration page lists what is needed in detail.
What if my source system is not on your list?
The other-panels page describes a general method that applies to any system that can export its data. Describe your system to [email protected] and we will tell you honestly what fits in the 30 working days.
What happens after the 30 working days?
Support for the move lasts the same 30 days. After that you keep the source code you downloaded and receive new source releases for the 12 months of the Source upgrade. Write to [email protected] about anything beyond that.

Sources and notes

The commercial terms come from the NexCMP pricing page and license terms. Facts about other products come from their official documentation, linked on each migration page. Trademarks belong to their owners.

Plan your migration with an engineer

Upgrade to NexCMP Source for $499 and start 30 working days of work with an expert, or write to [email protected] first.